21 West End Avenue, Retail 6
Project Overview
Integrated Projects (“IP”) is pleased to share project deliverables to the Dermot Company (the “Client”) for general contracting services for the interior white-boxing and addition of (1) ADA-compliant bathrooms at the following 728 square foot commercial location (the “Project”): 21 West End Avenue, Retail Unit 6. Integrated Projects managed and performed labor services, permitting, and held the necessary insurances to execute the base scope of work at the above referenced location.
Project Timeline
Design Start:
09/13/2018
Construction Start:
10/04/2018
Construction Completion:
11/06/2018
Approved GC Permit:
11/09/2018
Approved Mechanical Permit:
01/09/2019
DOB Sign-Offs:
02/04/2019
People
Owner / Client:
The Dermot Company, Justin Farenga
Project Executive:
Jose Cruz
jose@integratedprojects.co
Project Architect, AOR:
Ilya Chistiakov, RA
Project Engineer, EOR:
Mmdoh Megale, PE
Project Designer:
Allen Ghaida, Joseph Ghaida
GC License:
Antonio Bruno, GC 614947
Filing Set
Integrated Projects has consolidated all Building Information for this space within the “Filing Set”
BIM + CAD Files
Download the BIM, CAD, and Point Cloud files for this location.
Virtual Tour: Before Construction
See the following virtual tour for a record of the project site before construction.
Virtual Tour: As-Built
Enable all Project Stakeholders to view the location. Virtually coordinate in high-resolution — with a simple shareable link. Click below to open the full screen tour for best viewing.
Construction Site Photos
Download site photos of construction progress for this location, as captured from start to finish.